- May 28, 2011
- Signed contract with Ryan Homes sales representative
- June 1, 2011
- Met with NVR Mortgage
- June 3, 2011
- Met with sales representative to select some options
- June 9, 2011
- Met with Creative Flooring to choose flooring options
- June 14, 2011
- Received initial mortgage approval (numbers will change later)
- June 17, 2011
- Met with Guardian to choose security, home audio, data, TV and phone options
- June 26, 2011
- Met with sales representative to put down a 5% deposit
- August 6, 2011
- Visited Michener II model in Brunswick, MD
- August 22, 2011
- Pre-construction meeting
September 6, 2011(nope)September 7, 2011(still nothing)September 8, 2011(not a sausage)September 9, 2011(nary a shovel)September 10, 2011(zilch)September 12, 2011(not yet)September 13, 2011(unlucky 13)September 14, 2011(permit problems are holding this up)September 26, 2011(some stakes, some grass, no digging)September 27, 2011(another day, another delay)September 28, 2011(perhaps I should get my own shovel)September 29, 2011(more thumb twiddling)September 30, 2011(permit expected next week)October 5, 2011(not quite yet)October 6, 2011(this is getting ridiculous)October 7, 2011(two diggers parked on lot)October 8, 2011(some trees planted nearby)- October 10, 2011
- Broke ground
- October 13, 2011
- Foundation footings
- October 20, 2011
- Foundation formwork added
- October 21, 2011
- Foundation formwork removed
- October 27, 2011
- Waterproofing and plumbing
- October 28, 2011
- Backfilling completed and lumber delivered
- October 31, 2011
- Basement and garage prepared for pouring
- November 1, 2011
- Pre-pouring inspection
- November 2, 2011
- Basement and garage poured
- November 4, 2011
- Framing started
- November 15, 2011
- Shingles go up, interior plumbing and HVAC work started
- November 16, 2011
- Met with PM to discuss positioning of extra outlets
- November 21, 2011
- On-site meeting with Guardian to discuss positioning of audio/TV/data jacks
- November 28, 2011
- Pre-drywall meeting, received appraisal (97.9% of final sales price)
- November 29, 2011
- Locked-in mortgage interest rate
- December 1, 2011
- Independent pre-drywall inspection
- December 2, 2011
- Drywall hanging, siding work started
- January 6, 2012
- Pre-settlement walkthrough, independent pre-settlement inspection
- January 12, 2012
- Settlement
- January 13, 2012
- Deliveries (fridge, storage container, rugs, etc.)
- January 16, 2012
- Moving day
- April, 24, 2012
- Landscaping put it
- April, 25, 2012
- Sod put down
We have built a Ryan Homes Michener II in a development called Sadsbury Park.